Saturday, December 8, 2012

CBS Production & Distribution Move Next April

Staff at Canadian Blood Services learning the start date to move production and distribution to Dartmouth is now scheduled for April, 13th, 2013.

In a release, Public Affairs Manager Paul McGrath says the new production and distribution site in Dartmouth is finished and currently undergoing validation and commissioning.

Halifax functions will begin being consolidated into the Dartmouth site in February and March.


The Dartmouth Production and Distribution Site will be fully operational by the time the Saint John operations move next spring.

CBS is working with the Provincial Medical Society and others to ensure the province continues to receive the same or an improved level of service when Saint John production and distribution move to Dartmouth.

The process will be monitored before and after to ensure service levels are maintained at the same or an improved level.