Tuesday, January 24, 2012

What is Next For The Garcelon?

What is the next step for the Garcelon Civic Centre?

 Town Manager John Ferguson tells Tide News some activity will include stockpiling fill, approximately 7 metres high, designed to weigh down a specific area of property, compacting the land, to support the future pool.

He adds, that stockpile mimics years and years of compaction, and the process will take around 2 months to complete.

Project Manager Announced for Civic Center

It's a big step towards our new Civic Center.

Last night, St. Stephen Town Council approved E.A. Farren Limited from Saint John as the Project Management for the Garcelon Civic Center, for a price just over $439 thousand dollars.

Town Manager John Ferguson says there were 6 companies who applied for the position.

He says E.A. Farren had the lowest price with no potential for cost overruns.