The first section of concrete for footings being poured this morning.
That word from St. Stephen's Chief Administrative Officer John Ferguson on the Garcelon Civic Centre.
Ferguson tells Tide News the surcharge for the pool is now complete, as well as water and sewer connections have been installed.
The next step is completing the wooden forms for footings and rebar, which are about 90% done.
Ferguson says this part of the construction is scheduled to be completed for the end of October 2012.